For a contract, costs incurred to date are Rs 40,00,000, work certified is Rs 50,00,000, work uncertified is valued at Rs 4,00,000 at cost, and cash received is Rs 45,00,000. Using the conventional notional profit approach, what is the notional profit? (Costs incurred to date of Rs 40,00,000 include the cost of the uncertified work.)

Notional profit = 50,00,000 + 4,00,000 - 40,00,000 = Rs 14,00,000.

  1. ARs 10,00,000
  2. BRs 14,00,000Correct
  3. CRs 6,00,000
  4. DRs 9,00,000

Explanation

Notional profit = value of work certified + cost of work uncertified - total cost incurred to date. Costs of Rs 40,00,000 include the uncertified work, which is carried as work in progress at cost. So notional profit = 50,00,000 + 4,00,000 - 40,00,000 = Rs 14,00,000. Rs 10,00,000 ignores the uncertified work. Rs 6,00,000 wrongly subtracts it. Rs 9,00,000 is based on cash received, which is not used for notional profit.

Did you get it right without looking?

One question tells you little. A timed set on Contract Costing shows your real accuracy, how long you take and where you lose marks.

More Contract Costing questions