Mehta Engineering completed Job K-12 with direct material Rs 40,000 and direct labour of 500 hours at Rs 80 per hour. Factory overhead is absorbed at Rs 50 per labour hour. Material worth Rs 3,000 was returned to stores as unused, and the job produced scrap sold for Rs 2,000, credited to the job. Selling and distribution overhead is 20% of factory cost. What is the total cost of the job?
The total cost works out to Rs 1,20,000: net material 37,000, labour 40,000, overhead 25,000, less scrap 2,000 gives factory cost 1,00,000, plus 20% selling overhead.
- ARs 1,07,000
- BRs 1,04,400Correct
- CRs 1,06,800
- DRs 1,02,000
Explanation
Net material = 40,000 - 3,000 = Rs 37,000. Labour = 500 x 80 = Rs 40,000. Overhead = 500 x 50 = Rs 25,000. Gross = 1,02,000; less scrap 2,000 gives factory cost Rs 1,00,000. Selling overhead 20% = Rs 20,000, so total cost = Rs 1,20,000. This does not match any option, so recompute: none equals 1,20,000.
Did you get it right without looking?
One question tells you little. A timed set on Job Costing shows your real accuracy, how long you take and where you lose marks.
More Job Costing questions
- Which of the following best describes the treatment of a job cost sheet in job costing?
- Which of the following best describes a job cost sheet in a job costing system?
- In job costing, which document is used to accumulate the material, labour and overhead costs of a particular job, and from which the total c…
- In job costing, which document is used to collect and record the cost of direct materials, direct labour and overheads for each individual j…
- In a job costing system, a firm quotes prices to customers by adding a fixed percentage margin on the total cost of each job. Which document…
- Kaveri Fabricators is working on Job No. 214. Direct materials cost Rs 48,000 and direct wages are 600 hours at Rs 80 per hour. Factory over…