Rohan Infra Ltd is building a bridge under a construction contract for the State Roads Department. Its accountant lists the following costs for the year. Which one should NOT be included in the contract costs under AS 7?
Depreciation of a crane that is idle and not used on any contract is excluded. AS 7 allows only costs that relate directly to the contract or can be attributed to contract activity, so site supervision, specific design and specific plant insurance are included, but idle plant depreciation is not.
- AWages of the site supervisors engaged only on the bridge
- BDepreciation of a crane that is idle and not used on any contractCorrect
- CCost of design and technical assistance directly related to the bridge
- DInsurance premium on plant used specifically for the bridge
Explanation
AS 7 includes costs that relate directly to the contract, such as site labour, design costs directly related to it, and insurance of plant used on it. Depreciation of idle plant not used on any contract is not attributable to contract activity, so it is charged to the statement of profit and loss and is not a contract cost.
Did you get it right without looking?
One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.
More AS 7 Construction Contracts questions
- Malwa Constructions Ltd. has a contract for Rs 90 lakh. Up to the reporting date, costs incurred are Rs 54 lakh, which include Rs 6 lakh of …
- Sagar Constructions Ltd has a fixed price contract of ₹80 lakh. Estimated total cost is ₹60 lakh throughout the contract. Costs incurred are…
- At the year end, Kaveri Engineering Ltd has one contract in progress. Contract costs incurred to date are ₹900 lakh, recognised profits are …
- Navjyot Constructions is building a bridge for a state government. Its accountant is listing items for the contract cost under AS 7. Which o…
- Himalaya Projects Ltd has a fixed-price contract of ₹200 lakh with total estimated contract cost of ₹150 lakh. Costs incurred to date are ₹9…
- Sutlej Engineers has a fixed price contract with an original price of ₹200 lakh. The customer has approved a variation adding ₹20 lakh, whic…