CMA Final · Strategic Cost Management · Quality Cost Management
Sundaram Auto Components reports the following quality costs for a month: quality training Rs. 40,000; incoming material inspection Rs. 25,000; rework of defective units Rs. 60,000; warranty repairs Rs. 90,000; supplier quality audits Rs. 15,000; scrap Rs. 30,000. What is the total prevention plus appraisal cost?
The total is Rs. 80,000. Training and supplier audits are prevention costs totalling Rs. 55,000, and incoming inspection of Rs. 25,000 is appraisal. Rework, scrap and warranty repairs are failure costs and are excluded from this total.
- ARs. 80,000Correct
- BRs. 65,000
- CRs. 95,000
- DRs. 1,10,000
Explanation
Prevention costs are quality training (40,000) and supplier quality audits (15,000), giving 55,000. Appraisal is incoming inspection, 25,000. Total = 55,000 + 25,000 = 80,000. Rs. 65,000 wrongly leaves out the supplier audits and counts training only with inspection... Rs. 1,10,000 wrongly adds scrap, which is internal failure.
Did you get it right without looking?
One question tells you little. A timed set on Quality Cost Management shows your real accuracy, how long you take and where you lose marks.
More Quality Cost Management questions
- Tapti Plastics reports sales of Rs. 50,00,000 for the year. Its quality costs are prevention Rs. 2,00,000, appraisal Rs. 3,00,000, internal …
- Sundaram Pumps reports these quarterly quality figures: supplier quality training Rs. 40,000; incoming material inspection Rs. 90,000; scrap…
- Narmada Pumps makes 10,000 units a year. Present quality costs: prevention Rs. 1,00,000, appraisal Rs. 1,50,000, internal failure Rs. 3,00,0…
- Sundaram Pumps reports these annual quality costs: supplier quality audits Rs. 1,20,000; warranty repairs Rs. 2,50,000; final inspection Rs.…
- Godavari Textiles produces 8,000 metres of fabric per batch. Prevention and appraisal currently cost Rs. 1,20,000 per batch. 5% of output is…
- In a cost of quality framework, the 'conformance' costs consist of: