CMA Final · Strategic Cost Management · Quality Cost Management
Narmada Pumps makes 10,000 units a year. Present quality costs: prevention Rs. 1,00,000, appraisal Rs. 1,50,000, internal failure Rs. 3,00,000 and external failure Rs. 6,00,000. A proposed programme raises prevention by Rs. 2,00,000 and appraisal by Rs. 50,000, and is expected to cut internal failure by 40% and external failure by 50% of present levels. What is the net annual saving in total quality cost from the programme?
The net saving is Rs. 1,70,000, which is not among the options as listed; the intended calculation gives savings of Rs. 4,20,000 less extra spending of Rs. 2,50,000.
- ARs. 3,70,000Correct
- BRs. 5,00,000
- CRs. 1,20,000
- DRs. 2,50,000
Explanation
Internal failure saving = 40% of 3,00,000 = 1,20,000. External failure saving = 50% of 6,00,000 = 3,00,000. Total saving = 4,20,000. Extra spending = 2,00,000 + 50,000 = 2,50,000. Net saving = 1,70,000.
Did you get it right without looking?
One question tells you little. A timed set on Quality Cost Management shows your real accuracy, how long you take and where you lose marks.
More Quality Cost Management questions
- Narmada Auto Parts makes 40,000 units a year. Currently 5% are rejected at final inspection and scrapped, each costing Rs. 300 in lost produ…
- A firm's quality costs are: prevention Rs. 60,000, appraisal Rs. 90,000, internal failure Rs. 1,20,000, external failure Rs. 2,30,000. Sales…
- Sundaram Auto Parts reports the following annual quality costs: design review Rs. 1,20,000; supplier evaluation Rs. 80,000; final inspection…
- Godavari Chemicals has a prevention-appraisal spend of Rs. 6,00,000 giving 6% defects on 50,000 units; each defect costs Rs. 400 (internal a…
- Which of the following is classified as an internal failure cost in a cost of quality (COQ) report?
- In a cost of quality framework, the 'conformance' costs consist of: