CMA Final · Strategic Cost Management · Network Analysis - PERT, CPM
The critical path of a project has three activities with (optimistic, pessimistic) times of (2, 14), (5, 11) and (1, 13) days. Its expected length is 40 days. Assuming a normal distribution of project duration, what is the probability of completing within 46 days? (Use Φ(1)=0.8413, Φ(2)=0.9772, Φ(0.67)=0.7486.)
The probability is 97.72%. The critical path variance is 4+1+4 = 9, so the standard deviation is 3 days. Z = (46−40)/3 = 2, and the normal table gives 0.9772. Dividing by the variance instead of the standard deviation would be an error.
- A74.86%
- B84.13%
- C97.72%Correct
- D50.00%
Explanation
Activity variances are ((b-a)/6)^2 = 4, 1 and 4, so the path variance is 9 and the standard deviation is 3. Z = (46-40)/3 = 2, giving a probability of 0.9772. Using 9 instead of 3 as the standard deviation gives Z = 0.67 and 74.86%, which is wrong.
Did you get it right without looking?
One question tells you little. A timed set on Network Analysis - PERT, CPM shows your real accuracy, how long you take and where you lose marks.
More Network Analysis - PERT, CPM questions
- In a CPM network, activity 4-5 has a duration of 5 days. The earliest start time of its tail event 4 is day 12, the earliest occurrence time…
- The indirect cost of a project is Rs 3,000 per day. A critical activity can be crashed by up to 4 days at an extra direct cost of Rs 2,500 p…
- In a project network, activity D has an earliest start time of day 8, a duration of 5 days and a latest finish time of day 20. What is the t…
- In a PERT network the critical path has an expected duration of 50 days. The variances of its four activities are 4, 9, 4 and 8 days squared…
- The critical path of a PERT network of Gujarat Pumps Ltd has three activities with these (optimistic, most likely, pessimistic) times in day…
- A critical activity at Sundaram Constructions has a normal duration of 10 days at a cost of ₹50,000 and a crash duration of 7 days at a cost…