CMA Final · Strategic Cost Management · Network Analysis - PERT, CPM
In a CPM network, activity 4-5 has a duration of 5 days. The earliest start time of its tail event 4 is day 12, the earliest occurrence time of its head event 5 is day 22, and the latest occurrence time of event 5 is day 26. What is the free float of activity 4-5?
Free float is 5 days. It equals the head event's earliest time (22) minus the tail event's earliest time (12) minus the activity duration (5). The value 9 days would be total float, which uses the head event's latest time of 26 instead.
- A5 daysCorrect
- B9 days
- C10 days
- D4 days
Explanation
Free float = earliest time of head event − earliest time of tail event − duration = 22 − 12 − 5 = 5 days. The 9 days option is total float, which uses the latest time of the head event (26 − 12 − 5). The 10 days option forgets to deduct the activity duration.
Did you get it right without looking?
One question tells you little. A timed set on Network Analysis - PERT, CPM shows your real accuracy, how long you take and where you lose marks.
More Network Analysis - PERT, CPM questions
- A project has a single critical path of three activities, and no other path becomes critical during the crashing considered here. Activity A…
- Activity X takes 6 days. The tail event has an earliest time of day 10 and a latest time of day 12. The head event has an earliest time of d…
- The indirect cost of a project is Rs 3,000 per day. A critical activity can be crashed by up to 4 days at an extra direct cost of Rs 2,500 p…
- In a PERT network the critical path has an expected duration of 50 days. The variances of its four activities are 4, 9, 4 and 8 days squared…
- The critical path of a PERT network of Gujarat Pumps Ltd has three activities with these (optimistic, most likely, pessimistic) times in day…
- A critical activity at Sundaram Constructions has a normal duration of 10 days at a cost of ₹50,000 and a crash duration of 7 days at a cost…