In a project network, activity D has an earliest start time of day 8, a duration of 5 days and a latest finish time of day 20. What is the total float of activity D?

The total float is 7 days. It is the latest finish time minus the earliest start time minus the duration, so 20 − 8 − 5 equals 7. Subtracting only the start time would give 12 and would ignore the time the activity itself uses.

  1. A12 days
  2. B3 days
  3. C15 days
  4. D7 daysCorrect

Explanation

Total float = latest finish − earliest start − duration = 20 − 8 − 5 = 7 days. Using 12 days ignores the activity duration. Using 3 days wrongly mixes the earliest finish (13) with other figures instead of computing 20 − 13 = 7.