CMA Final · Strategic Financial Management · Evaluation of Risky Proposals for Investment Decisions

Tulsi Auto's project has an expected NPV of Rs 5,00,000 and a standard deviation of Rs 4,00,000. NPV is assumed to be normally distributed. What is the z-value for the NPV of zero, i.e., the point at which the project breaks even?

The z-value is the break-even NPV of zero less the mean of Rs 5,00,000, divided by the standard deviation of Rs 4,00,000. This gives -1.25, negative because zero lies below the expected NPV.

  1. A-1.25Correct
  2. B1.25
  3. C-0.80
  4. D0.80

Explanation

z = (0 - 5,00,000)/4,00,000 = -1.25. The sign is negative because zero lies below the mean. A positive 1.25 would ignore the direction; 0.80 inverts the ratio.