CMA Final · Strategic Cost Management · Network Analysis - PERT, CPM
Two critical activities of a project, A and B, are in series, and no other path will become critical during crashing. Activity A can be crashed by at most 2 days at Rs 3,000 per day. Activity B can be crashed by at most 3 days at Rs 4,500 per day. Every day saved reduces indirect cost by Rs 3,800. Which crashing decision gives the maximum net saving?
Crash only activity A for 2 days, giving a net saving of Rs 1,600. A's Rs 3,000 daily cost is below the Rs 3,800 indirect saving, but B's Rs 4,500 exceeds it, so crashing B would reduce the net benefit to Rs 900.
- ACrash 2 days (A only), net saving Rs 1,600Correct
- BCrash 3 days (A 2 days and B 1 day), net saving Rs 900
- CCrash 1 day (A only), net saving Rs 800
- DDo not crash, net saving nil
Explanation
Crash the cheapest activity first. Crashing A for 2 days costs 6,000 and saves 7,600 in indirect cost, a net saving of 1,600. A third day via B costs 4,500, which is more than the 3,800 saved, so net saving falls to 900 (cost 10,500 against saving 11,400). One day gives only 800.
Did you get it right without looking?
One question tells you little. A timed set on Network Analysis - PERT, CPM shows your real accuracy, how long you take and where you lose marks.
More Network Analysis - PERT, CPM questions
- In a PERT network the critical path has an expected duration of 50 days. The variances of its four activities are 4, 9, 4 and 8 days squared…
- The critical path of a PERT network of Gujarat Pumps Ltd has three activities with these (optimistic, most likely, pessimistic) times in day…
- A critical activity at Sundaram Constructions has a normal duration of 10 days at a cost of ₹50,000 and a crash duration of 7 days at a cost…
- In a project network, activity P has earliest start 6, duration 5, and its successor Q has latest start 14. P has no other successor. What i…
- A PERT network has two paths: A-C and B-D. Three-point estimates (optimistic, most likely, pessimistic, in days) are: A (2, 5, 8), C (4, 7, …
- In a project network, activity D has an earliest start time of day 8, a duration of 5 days and a latest finish time of day 20. What is the t…