Which of the following best describes a 'cost-plus' job contract as used in job costing?

A cost-plus job contract fixes the price as the actual cost of the job plus an agreed profit, expressed as a percentage or a fixed fee. The customer bears the cost variation, unlike a fixed-price contract where the contractor bears any overrun.

  1. AThe selling price is fixed in advance and the contractor bears any cost overrun
  2. BThe contract price is the actual cost of the job plus an agreed percentage or fixed fee as profitCorrect
  3. CThe price is determined by the market rate for similar jobs irrespective of cost
  4. DThe job is costed only on direct material, with overheads ignored

Explanation

In a cost-plus contract the customer pays the actual cost incurred on the job plus an agreed margin, either as a percentage or a fixed fee. Option A describes a fixed-price contract, where the contractor carries the cost overrun risk.