CMA Intermediate · Operations Management and Strategic Management · Scheduling and Queuing Models
Which of the following is a typical objective of scheduling in an operations system?
A typical scheduling objective is to meet due dates while minimising work-in-process inventory, job waiting time and idle time of resources. Maximising idle time, increasing set-up times or deliberately delaying jobs would raise cost and harm delivery performance, so they are not objectives.
- AMaximising idle time of machines to keep reserve capacity
- BMinimising work-in-process inventory and job waiting time while meeting due datesCorrect
- CIncreasing set-up times to improve flexibility
- DDelaying all jobs until the due date has passed
Explanation
Scheduling aims to meet delivery dates, reduce flow time, WIP and idle time, and use resources well. The other options describe outcomes that raise cost or cause delay, so they are not objectives.
Did you get it right without looking?
One question tells you little. A timed set on Scheduling and Queuing Models shows your real accuracy, how long you take and where you lose marks.
More Scheduling and Queuing Models questions
- Mehta Fabricators receives an order that must be delivered on 30 June. The planner starts from 30 June and works back through each operation…
- In Johnson's rule for sequencing n jobs through two machines (M1 then M2), which step correctly describes how the optimal sequence is built?
- A bank branch has 3 tellers working as an M/M/3 system. Customers arrive at an average of 20 per hour and each teller serves an average of 1…
- In production scheduling, a Gantt load chart is primarily used to show which of the following?
- In the standard M/M/1 queuing model, the first M, the second M and the 1 respectively describe:
- Johnson's rule gives an optimal sequence for which of the following situations?