CMA Intermediate · Operations Management and Strategic Management · Scheduling and Queuing Models
Which statement best distinguishes a Gantt progress chart from a Gantt load chart?
A Gantt progress chart compares actual progress or output of jobs against the planned schedule, supporting control, whereas a Gantt load chart shows how much work is assigned to each machine or work centre over time, supporting loading decisions.
- AA progress chart compares actual output with planned output for jobs over time, while a load chart shows work assigned to resourcesCorrect
- BA progress chart shows machine idle time only, while a load chart shows job costs
- CA progress chart is used only for inventory, while a load chart is used only for quality control
- DThere is no difference; both show the same information in the same format
Explanation
A Gantt progress (or record) chart tracks actual performance against the plan for each job, helping control. A load chart shows the allotment of work to machines or centres. The other options assign incorrect purposes to the charts.
Did you get it right without looking?
One question tells you little. A timed set on Scheduling and Queuing Models shows your real accuracy, how long you take and where you lose marks.
More Scheduling and Queuing Models questions
- In Johnson's rule for sequencing n jobs through two machines (M1 then M2), which step correctly describes how the optimal sequence is built?
- For an M/M/s queue with s = 2, λ = 6 per hour and μ = 4 per hour per channel, which of the following is the correct value of P0 using P0 = 1…
- A machine shop at Pune has 8 working hours per day and runs 5 days in a planning week. Machine M1 is already loaded with jobs needing 26 hou…
- At a toll plaza lane modelled as M/M/1, vehicles arrive at an average of 40 per hour and the booth serves an average of 50 per hour. What is…
- In the standard M/M/1 queuing model, the first M, the second M and the 1 respectively describe:
- Mehta Fabricators receives an order that must be delivered on 30 June. The planner starts from 30 June and works back through each operation…