CMA Intermediate · Operations Management and Strategic Management · Production Planning and Control
Which statement correctly distinguishes MRP II from basic MRP?
MRP II extends basic MRP by integrating capacity planning, shop floor control and financial planning with material planning. It still relies on the master production schedule and bill of materials, so it is a wider resource planning system, not a simpler reorder-point method.
- AMRP II extends MRP by integrating capacity planning, shop floor control and financial planning with material planningCorrect
- BMRP II is a simpler method that ignores the bill of materials and uses only reorder points
- CMRP II deals only with the purchase of raw materials and excludes production scheduling
- DMRP II replaces the master production schedule with a continuous kanban pull system
Explanation
MRP II (Manufacturing Resource Planning) builds on MRP by closing the loop with capacity requirements planning, shop floor control, and links to finance and marketing. It still uses the BOM and MPS. The kanban option describes JIT, not MRP II.
Did you get it right without looking?
One question tells you little. A timed set on Production Planning and Control shows your real accuracy, how long you take and where you lose marks.
More Production Planning and Control questions
- In a manufacturing firm, the plan that sets monthly output, workforce and inventory levels for product families over roughly the next 6 to 1…
- In a Material Requirement Planning (MRP) system, which of the following is the primary input that states the quantity and timing of the fini…
- A plant works one shift of 8 hours per day for 25 days in a month. Each machine is available for 90% of scheduled time, and there are 10 ide…
- In production planning and control, which activity specifically involves fixing the sequence in which jobs will be processed on each machine…
- A plant manufactures a wide variety of low-volume, customised products, with each product following a different sequence of operations throu…
- A production manager uses a chart with horizontal bars drawn against a time scale to compare planned and actual progress of jobs on each mac…