ACCA Strategic Professional · Strategic Business Leader · Leading and managing projects
Zenith Retail plc is implementing a new warehouse system. During planning, the project manager lists possible events such as supplier delay, key staff departure and data migration failure. For each she records the likelihood and the impact on cost and time, then ranks them. Which risk management step is being carried out?
The project manager is performing risk assessment. Having already listed the risks, she now estimates likelihood and impact and ranks them, which is analysis and evaluation. Identification only produces the list, while monitoring and transfer happen later as part of response and control.
- ARisk identification only
- BRisk assessment (analysis and evaluation)Correct
- CRisk monitoring and review
- DRisk transfer
Explanation
Listing events is identification, but recording likelihood and impact and ranking the risks is assessment, which is analysis and evaluation. Identification alone would stop at the list. Monitoring occurs later during execution, and transfer is a response such as insurance or contracting out.
Did you get it right without looking?
One question tells you little. A timed set on Leading and managing projects shows your real accuracy, how long you take and where you lose marks.
More Leading and managing projects questions
- Harlow Freight, a logistics company, is considering a new warehouse automation system. The board asks the project sponsor to explain why the…
- Zenara Foods plans to launch a new regional distribution hub. The board describes it as a one-off undertaking with a defined start and end d…
- Bramwell Co is planning a product launch project. The activities are: A (3 weeks, no predecessor), B (5 weeks, after A), C (2 weeks, after A…
- Brindle Telecom is at the start of a customer-portal project. The project manager wants the sponsor to confirm early on that the project is …
- During a bank's core systems upgrade, the project team has entered a phase of open disagreement. Two senior analysts challenge the approach,…
- Corvane Engineering is running a large project. The sponsor wants it completed two months early without increasing cost or reducing quality.…