CMA Intermediate · Operations Management and Strategic Management · Lean Operations and JIT
A Hosur plant uses kanban. Demand is 480 units per day, each container holds 20 units, a container takes 0.5 day to cycle (production, transport, waiting, return) and the safety factor is 10%. Number of kanban containers needed = demand x cycle time x (1 + safety factor) / container size. How many kanbans are required?
The firm needs 14 kanban containers. Demand during the 0.5-day cycle is 240 units, which becomes 264 units with a 10% safety factor. Dividing by the container size of 20 gives 13.2, and since containers are whole, the number is rounded up to 14.
- A12
- B13Correct
- C14
- D27
Explanation
Demand during cycle = 480 x 0.5 = 240 units. With 10% safety = 264 units. Dividing by 20 gives 13.2, which is rounded up to 14 whole containers... but check: 264/20 = 13.2, so rounding up gives 14. Correct answer is 14.
Did you get it right without looking?
One question tells you little. A timed set on Lean Operations and JIT shows your real accuracy, how long you take and where you lose marks.
More Lean Operations and JIT questions
- According to the five principles of lean thinking, what should be the starting point for defining value?
- A textile mill in Surat polishes the back side of fabric rolls to a mirror finish although customers never see or specify this finish. Which…
- In a Kanban-based pull production system, what normally authorises an upstream work centre to start producing a batch of parts?
- A Pune auto-component plant makes batches far larger than customer orders need, so finished goods pile up in the warehouse. Which category o…
- In lean operations, the term 'muda' refers to which of the following?
- In a Chennai auto-component plant, operators walk 40 metres to fetch a gauge from a distant cabinet several times each shift. Which waste is…