CMA Intermediate · Operations Management and Strategic Management · Lean Operations and JIT
A Pune auto-component plant makes batches far larger than customer orders need, so finished goods pile up in the warehouse. Which category of lean waste does this best illustrate?
This is overproduction, the waste of making more or earlier than customers require. It is considered the worst lean waste because it breeds other wastes such as excess inventory, storage space and handling. Waiting, over-processing and motion refer to idle time, excess work on a unit and unnecessary movement.
- AWaiting
- BOverproductionCorrect
- COver-processing
- DUnnecessary motion
Explanation
Producing more or earlier than the customer demands is overproduction, regarded as the most serious waste because it causes excess inventory, storage and handling. Waiting concerns idle time, over-processing concerns doing more work than required on a unit, and motion concerns operator movement.
Did you get it right without looking?
One question tells you little. A timed set on Lean Operations and JIT shows your real accuracy, how long you take and where you lose marks.
More Lean Operations and JIT questions
- A plant uses a Kanban system for a part with 600 units of daily demand, container size 25 units, and 12 Kanbans in circulation, with no safe…
- A Kanban system for a component has daily demand of 400 units, lead time (processing plus waiting plus transit) of 0.5 day, a safety stock p…
- During JIT implementation at a Gurugram appliance plant, management trains operators to stop the line when a defect appears and to fix the r…
- In lean operations, the term 'muda' refers to which of the following?
- According to the five principles of lean thinking, what should be the starting point for defining value?
- A Hosur plant uses kanban. Demand is 480 units per day, each container holds 20 units, a container takes 0.5 day to cycle (production, trans…