A line has a cycle time of 5 minutes and total task time of 18 minutes per unit. Using the minimum whole number of workstations, what is the balance efficiency?
Balance efficiency is 90%. The minimum stations are 18 divided by 5, which is 3.6, rounded up to 4. Efficiency equals 18 divided by 4 times 5, that is 18 divided by 20, giving 90 percent.
- A90%Correct
- B72%
- C100%
- D80%
Explanation
Minimum stations = 18/5 = 3.6, rounded up to 4. Efficiency = total task time / (stations x cycle time) = 18/(4x5) = 18/20 = 90%. 72% wrongly uses 5 stations (18/25).
Did you get it right without looking?
One question tells you little. A timed set on Simulation and Line Balancing shows your real accuracy, how long you take and where you lose marks.
More Simulation and Line Balancing questions
- Under the ranked positional weight method of line balancing, how is the positional weight of a task calculated?
- A hospital in Pune builds a computer model of its outpatient clinic and runs it repeatedly with randomly generated patient arrival times to …
- A tea stall's daily demand has this distribution: 20 cups (probability 0.30), 30 cups (0.50), 40 cups (0.20). Random numbers 00-99 are assig…
- In assembly line balancing, the 'cycle time' of a line is best described as:
- Which statement about using simulation for inventory and queuing problems is correct?
- A line is balanced with 5 workstations and a cycle time of 6 minutes. The task times total 24 minutes. What are the balance delay (idle time…