CMA Intermediate · Operations Management and Strategic Management · Simulation and Line Balancing
A line is balanced with 5 workstations and a cycle time of 6 minutes. The task times total 24 minutes. What are the balance delay (idle time percentage) and efficiency?
Balance delay is 20% and efficiency is 80%. Five stations at 6 minutes give 30 minutes of capacity, of which 24 minutes is productive work. Idle time is 6 minutes, which is 20 percent of 30, and efficiency is the remaining 80 percent.
- ABalance delay 20%, efficiency 80%Correct
- BBalance delay 25%, efficiency 75%
- CBalance delay 4%, efficiency 96%
- DBalance delay 80%, efficiency 20%
Explanation
Available station time = 5 x 6 = 30 minutes. Idle = 30 - 24 = 6 minutes. Balance delay = 6/30 = 20%; efficiency = 24/30 = 80%. Using 4 stations (24/6) would wrongly ignore the fifth station actually in use.
Did you get it right without looking?
One question tells you little. A timed set on Simulation and Line Balancing shows your real accuracy, how long you take and where you lose marks.
More Simulation and Line Balancing questions
- In assembly line balancing, the 'cycle time' of a line is best described as:
- Which of the following is a recognised limitation of simulation as a decision tool?
- Under the ranked positional weight method of line balancing, how is the positional weight of a task calculated?
- A hospital in Pune builds a computer model of its outpatient clinic and runs it repeatedly with randomly generated patient arrival times to …
- A tea stall's daily demand has this distribution: 20 cups (probability 0.30), 30 cups (0.50), 40 cups (0.20). Random numbers 00-99 are assig…
- Which statement about using simulation for inventory and queuing problems is correct?