CMA Intermediate · Operations Management and Strategic Management · Simulation and Line Balancing
A tea stall's daily demand has this distribution: 20 cups (probability 0.30), 30 cups (0.50), 40 cups (0.20). Random numbers 00-99 are assigned as cumulative intervals in ascending order of demand. Which assignment is correct?
The correct assignment is 20 cups for 00-29, 30 cups for 30-79 and 40 cups for 80-99. Each demand level receives as many two-digit random numbers as its probability times 100, allotted cumulatively, so intervals are 30, 50 and 20 numbers long.
- A20 cups: 00-29; 30 cups: 30-79; 40 cups: 80-99Correct
- B20 cups: 00-30; 30 cups: 31-80; 40 cups: 81-99
- C20 cups: 01-30; 30 cups: 31-50; 40 cups: 51-70
- D20 cups: 00-19; 30 cups: 20-69; 40 cups: 70-99
Explanation
Cumulative probabilities are 0.30, 0.80 and 1.00. With two-digit numbers 00-99 (100 values), 20 cups gets 30 numbers (00-29), 30 cups gets 50 numbers (30-79), and 40 cups gets 20 numbers (80-99). Option 2 gives 31, 50 and 19 numbers, so it is wrong.
Did you get it right without looking?
One question tells you little. A timed set on Simulation and Line Balancing shows your real accuracy, how long you take and where you lose marks.
More Simulation and Line Balancing questions
- Which statement about using simulation for inventory and queuing problems is correct?
- A line has a cycle time of 5 minutes and total task time of 18 minutes per unit. Using the minimum whole number of workstations, what is the…
- A line is balanced with 5 workstations and a cycle time of 6 minutes. The task times total 24 minutes. What are the balance delay (idle time…
- In a Monte Carlo simulation of a shop's daily demand, the probability distribution is: 10 units (0.20), 20 units (0.50), 30 units (0.30). Cu…
- Tasks A (40 s), B (30 s), C (20 s), D (50 s), E (10 s) are assigned using the largest candidate rule with cycle time 80 s. Precedence: A pre…
- In assembly line balancing, the 'cycle time' of a line is best described as: