CMA Intermediate · Operations Management and Strategic Management · Designing of Operational Systems and Control
In an assembly line layout, the main purpose of line balancing is to:
Line balancing aims to distribute tasks among workstations so that each station's workload is close to the cycle time, which minimises idle time and improves line efficiency. It is not about adding stations, choosing plant location or building up work-in-process.
- AMaximise the number of workstations used
- BDistribute tasks among workstations so idle time is minimisedCorrect
- CLocate the plant close to raw material sources
- DIncrease work-in-process between stations
Explanation
Line balancing assigns tasks to stations so that station times are close to cycle time, reducing idle time and raising efficiency. More stations or more WIP does not achieve this.
Did you get it right without looking?
One question tells you little. A timed set on Designing of Operational Systems and Control shows your real accuracy, how long you take and where you lose marks.
More Designing of Operational Systems and Control questions
- A firm compares three sites using a weighted factor rating. Weights: labour 0.5, transport 0.3, power 0.2. Scores out of 100 for Site X are …
- In the product development process, which activity is carried out immediately after a firm has generated a set of product ideas and before i…
- Which decision is classified as a strategic-level (long-term) decision in operations management rather than a tactical or operational one?
- A firm uses a shared kitchen to serve both dine-in customers and a cloud-kitchen delivery app. Which feature most clearly distinguishes serv…
- A manufacturer in Chennai decides to build extra capacity ahead of expected demand growth, accepting the risk of idle capacity. Which capaci…
- In operations management, the transformation process converts inputs into outputs. Which of the following correctly pairs an input with the …