A plant uses a Kanban system for a part with 600 units of daily demand, container size 25 units, and 12 Kanbans in circulation, with no safety allowance. What is the maximum lead time (in days) that the system can support?
The system can support a lead time of 0.5 day. With 12 Kanbans of 25 units each, 300 units circulate, and at 600 units of daily demand that stock covers 300 divided by 600, which equals half a day.
- A0.50 dayCorrect
- B0.40 day
- C2.00 days
- D0.25 day
Explanation
Number of Kanbans = demand x lead time / container size, so lead time = 12 x 25 / 600 = 300/600 = 0.5 day. Option 0.40 uses a wrong container size; 2.00 inverts the ratio.
Did you get it right without looking?
One question tells you little. A timed set on Lean Operations and JIT shows your real accuracy, how long you take and where you lose marks.
More Lean Operations and JIT questions
- A Kanban system for a component has daily demand of 400 units, lead time (processing plus waiting plus transit) of 0.5 day, a safety stock p…
- During JIT implementation at a Gurugram appliance plant, management trains operators to stop the line when a defect appears and to fix the r…
- According to the five principles of lean thinking, what should be the starting point for defining value?
- A Hosur plant uses kanban. Demand is 480 units per day, each container holds 20 units, a container takes 0.5 day to cycle (production, trans…
- A textile mill in Surat polishes the back side of fabric rolls to a mirror finish although customers never see or specify this finish. Which…
- Which of the following is a recognised feature of a JIT manufacturing environment as distinct from a traditional manufacturing environment?