At a toll plaza lane modelled as M/M/1, vehicles arrive at an average of 40 per hour and the booth serves an average of 50 per hour. What is the traffic intensity (utilisation factor) and the average number of vehicles in the system?
Utilisation is 40/50 = 0.8 and the average number of vehicles in the system is 40/(50-40) = 4. The figure 3.2 is the average number waiting in the queue only, which excludes the vehicle currently being served.
- A0.8 and 4Correct
- B0.8 and 3.2
- C1.25 and 4
- D0.8 and 5
Explanation
Traffic intensity rho = lambda/mu = 40/50 = 0.8. Average number in system Ls = lambda/(mu - lambda) = 40/10 = 4. Using rho/(1-rho) = 0.8/0.2 = 4 confirms it. The value 3.2 is the average queue length Lq = rho x Ls, not the number in the system.
Did you get it right without looking?
One question tells you little. A timed set on Scheduling and Queuing Models shows your real accuracy, how long you take and where you lose marks.
More Scheduling and Queuing Models questions
- Four jobs are processed on M1 then M2 (hours): A (5, 2), B (1, 6), C (9, 7), D (3, 8). What is the optimal sequence under Johnson's rule?
- Four jobs are waiting at one machine with processing times (days) and due dates (days from today): A (4, 6), B (2, 9), C (6, 8), D (3, 5). J…
- In Johnson's rule for sequencing n jobs through two machines (M1 then M2), which step correctly describes how the optimal sequence is built?
- For an M/M/s queue with s = 2, λ = 6 per hour and μ = 4 per hour per channel, which of the following is the correct value of P0 using P0 = 1…
- A machine shop at Pune has 8 working hours per day and runs 5 days in a planning week. Machine M1 is already loaded with jobs needing 26 hou…
- In the standard M/M/1 queuing model, the first M, the second M and the 1 respectively describe: