CMA Intermediate · Operations Management and Strategic Management · Scheduling and Queuing Models
For an M/M/s queue with s = 2, λ = 6 per hour and μ = 4 per hour per channel, which of the following is the correct value of P0 using P0 = 1 / [Σ(n=0 to s−1) (λ/μ)^n/n! + (λ/μ)^s/(s!(1−ρ))]?
P0 equals 1/7. The sum of the first terms is 1 + 1.5 = 2.5, and the final term is 2.25 divided by 2 × 0.25, which is 4.5. The total is 7, so the probability of an empty system is 1/7.
- A1/7Correct
- B1/5
- C1/9
- D1/4
Explanation
λ/μ = 1.5, ρ = 0.75. Sum for n=0 to 1 = 1 + 1.5 = 2.5. Last term = 2.25/(2 × 0.25) = 4.5. Total = 7.0, so P0 = 1/7. Using (1−ρ) omitted gives 2.5 + 1.125 = 3.625, a wrong result.
Did you get it right without looking?
One question tells you little. A timed set on Scheduling and Queuing Models shows your real accuracy, how long you take and where you lose marks.
More Scheduling and Queuing Models questions
- In Johnson's rule for sequencing n jobs through two machines (M1 then M2), which step correctly describes how the optimal sequence is built?
- In the standard M/M/1 queuing model, the first M, the second M and the 1 respectively describe:
- Johnson's rule gives an optimal sequence for which of the following situations?
- A machine shop at Pune has 8 working hours per day and runs 5 days in a planning week. Machine M1 is already loaded with jobs needing 26 hou…
- Which of the following is a typical objective of scheduling in an operations system?
- In the standard multi-channel queuing model (M/M/s), which assumption about the service channels is made?