CMA Final · Strategic Cost Management · Network Analysis - PERT, CPM
For an activity in a PERT network, the optimistic time is 4 days, the most likely time is 10 days and the pessimistic time is 22 days. What is the expected time of the activity under the beta-distribution approximation?
The expected time is 11 days. PERT weights the most likely estimate four times, so the expected time is (4 + 4×10 + 22)/6 = 11. A simple average of the three estimates would give 12 days, which ignores the beta-distribution weighting.
- A10 days
- B11 daysCorrect
- C12 days
- D13 days
Explanation
PERT expected time = (a + 4m + b)/6 = (4 + 40 + 22)/6 = 66/6 = 11 days. The simple average (4 + 10 + 22)/3 = 12 days ignores the weight of 4 on the most likely time, so it is wrong.
Did you get it right without looking?
One question tells you little. A timed set on Network Analysis - PERT, CPM shows your real accuracy, how long you take and where you lose marks.
More Network Analysis - PERT, CPM questions
- Two critical activities of a project, A and B, are in series, and no other path will become critical during crashing. Activity A can be cras…
- For a PERT activity, the optimistic time is 4 days, the most likely time is 7 days and the pessimistic time is 16 days. What is the expected…
- For a PERT activity, the optimistic time is 4 days, the most likely time is 7 days and the pessimistic time is 16 days. What are the expecte…
- An activity in a PERT network has optimistic time 10 weeks, most likely time 16 weeks and pessimistic time 28 weeks. What are its expected t…
- In a CPM network, activity 4-5 has a duration of 5 days. The earliest start time of its tail event 4 is day 12, the earliest occurrence time…
- A project has a single critical path of three activities, and no other path becomes critical during the crashing considered here. Activity A…