CA Intermediate · Cost and Management Accounting · Overheads - Absorption Costing Method
Gupta Engineering Ltd. budgeted factory overheads of ₹6,00,000 and 40,000 direct labour hours for the year. Actual overheads were ₹6,30,000 and actual labour hours worked were 41,000. What is the amount of over-absorbed or under-absorbed overhead?
The predetermined rate is ₹15 per labour hour. Absorption on 41,000 actual hours is ₹6,15,000, while actual overhead is ₹6,30,000. Since less was absorbed than incurred, overheads are under-absorbed by ₹15,000.
- AUnder-absorbed by ₹15,000Correct
- BOver-absorbed by ₹15,000
- COver-absorbed by ₹30,000
- DUnder-absorbed by ₹30,000
Explanation
Rate = 6,00,000 ÷ 40,000 = ₹15 per hour. Absorbed = 41,000 × 15 = ₹6,15,000. Actual = ₹6,30,000. Absorbed is less than actual, so under-absorbed by ₹15,000. Choosing ₹30,000 results from comparing actual with budgeted overhead instead of absorbed overhead.
Did you get it right without looking?
One question tells you little. A timed set on Overheads - Absorption Costing Method shows your real accuracy, how long you take and where you lose marks.
More Overheads - Absorption Costing Method questions
- Kaveri Auto Parts uses the direct (non-reciprocal) method. Overheads before service allocation: Production P1 Rs 2,40,000, P2 Rs 1,80,000, S…
- Kaveri Industries absorbs factory overheads at ₹12 per direct labour hour. Budgeted overheads were ₹6,00,000 and actual overheads incurred w…
- Sundaram Fabrics absorbs factory overheads at a predetermined rate of Rs 15 per machine hour. During the year, actual machine hours were 40,…
- Surya Engineering has two production departments, P and Q, and two service departments, S1 and S2. Primary-distributed overheads are: P ₹2,4…
- A factory's machine shop budgeted overheads of Rs 4,80,000 for the year and 24,000 machine hours. Actual overheads were Rs 5,10,000 and actu…
- Gupta Engineering absorbs factory overheads at ₹12 per direct labour hour. Budgeted overheads were ₹6,00,000 for 50,000 direct labour hours.…