CMA Intermediate · Operations Management and Strategic Management · Project Management, Monitoring and Control
In a CPM project network, the critical path is best described as:
The critical path is the longest path in duration from start to end of the network. It determines the minimum project completion time, and its activities have zero float, so any delay in them delays the whole project.
- AThe path with the largest number of activities
- BThe longest path in terms of total duration from start to endCorrect
- CThe path with the highest total cost
- DThe shortest path in terms of total duration from start to end
Explanation
The critical path is the longest duration path through the network. It fixes the minimum project completion time, and activities on it have zero total float. The path with most activities need not be the longest in time, so the first option is wrong.
Did you get it right without looking?
One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.
More Project Management, Monitoring and Control questions
- The critical path of a project at Kaveri Constructions consists of three activities with expected times of 10, 14 and 16 days, and variances…
- An activity has optimistic time 6 days, most likely time 9 days and pessimistic time 18 days. What is the variance of its duration under PER…
- A project has a total budget at completion (BAC) of ₹20,00,000. Earned value to date is ₹8,00,000 and actual cost is ₹10,00,000. Assuming th…
- In the project life cycle, which phase is mainly concerned with defining objectives, scope, deliverables and obtaining approval to proceed?
- In a PERT network, an activity has optimistic time 4 days, most likely time 7 days and pessimistic time 16 days. Using the beta-distribution…
- A construction firm in Pune has completed building a warehouse and is now handing it over to the client, obtaining acceptance, releasing sta…