CMA Intermediate · Operations Management and Strategic Management · Project Management, Monitoring and Control
In a project network, a delay in an activity that has a total float of 6 days is 4 days. Assuming no other change, what is the effect on the project completion date?
The project completion date is unchanged because total float of 6 days can absorb the 4-day delay. Only the delay exceeding the float would push out the project end date, and here the activity merely uses up 4 days of its float.
- AThe project is delayed by 4 days
- BThe project is delayed by 2 days
- CThe project completion date is unchangedCorrect
- DThe project is delayed by 6 days
Explanation
Total float is the delay an activity can absorb without delaying project completion. A 4-day delay is less than the 6-day float, so the project end date does not change. The remaining float falls to 2 days. Option 'delayed by 2 days' wrongly subtracts float from the delay.
Did you get it right without looking?
One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.
More Project Management, Monitoring and Control questions
- A project has a budgeted cost of work scheduled (planned value) of ₹8,00,000 to date, earned value of ₹6,40,000 and actual cost of ₹7,20,000…
- For an activity in a CPM network, the earliest start (ES) is 8 days, duration is 5 days, and the latest finish (LF) is 18 days. What is its …
- Which statement about free float and total float in a CPM network is correct?
- An activity has a normal time of 10 days at a normal cost of ₹40,000 and a crash time of 6 days at a crash cost of ₹52,000. Assuming linear …
- A project has an expected duration of 40 days with a standard deviation of 4 days on its critical path. Given the normal distribution, the a…
- During project monitoring, a negative cost variance (CV = EV − AC) indicates which situation?