CMA Final · Strategic Cost Management · Activity Based Cost Management
Under activity based cost management, an activity of 'rework of defective output' is classified as non-value-adding. Which action best reflects the ABM response?
The ABM response is to eliminate or reduce rework by fixing the root cause of defects. Rework adds no value the customer pays for, so the aim is to cut the waste itself rather than reallocate its cost or inflate driver volume.
- AEliminate or reduce the activity by fixing the root cause of defectsCorrect
- BReallocate its cost to products on machine hours
- CTreat it as a value-adding activity if customers pay for the final product
- DIncrease its cost driver volume to lower the rate per unit
Explanation
ABM seeks to reduce or eliminate non-value-adding activities through root-cause removal. Reallocating costs only changes the apportionment and does not cut waste. Raising driver volume reduces the rate but not the real cost, so it is wrong.
Did you get it right without looking?
One question tells you little. A timed set on Activity Based Cost Management shows your real accuracy, how long you take and where you lose marks.
More Activity Based Cost Management questions
- Kaveri Components Ltd has a quality inspection cost pool of Rs 3,60,000 with a cost driver of number of inspections, total 1,200 inspections…
- Meera Foods Ltd has a distribution activity pool of Rs 9,00,000. The practical capacity is 6,000 deliveries, but only 4,500 deliveries are e…
- Under activity based costing, the cost of 'product design modification', which is incurred for each product line regardless of the number of…
- Under activity based management, a non-value-added activity such as rework of defective output is best handled by:
- Kaveri Textiles has a material-handling pool of Rs 4,80,000 and uses the number of material movements as the driver. Budgeted movements are …
- In an activity based costing system, which of the following is the best example of a batch-level activity?