ACCA Strategic Professional · Strategic Business Leader · Leading and managing projects
Orrin Pharma is planning a clinical data system. The project manager defines acceptance criteria, agrees test standards and reviews the development process with the supplier before any coding starts, rather than relying on a final inspection. Which approach to quality does this represent?
This is quality assurance within quality planning: setting acceptance criteria and standards and reviewing processes before work starts so defects are prevented. It differs from quality control, which only inspects finished deliverables to detect defects after they have occurred.
- AQuality assurance and planned quality built into the process, with prevention preferred to inspectionCorrect
- BQuality control only, based on detecting defects in finished deliverables
- CCrashing, to shorten the schedule at additional cost
- DFast-tracking, to overlap dependent activities
Explanation
Defining criteria and standards up front and reviewing processes is quality planning and assurance, which aims to prevent defects. Quality control is inspection of outputs after production. Crashing and fast-tracking are schedule compression techniques, unrelated to quality management.
Did you get it right without looking?
One question tells you little. A timed set on Leading and managing projects shows your real accuracy, how long you take and where you lose marks.
More Leading and managing projects questions
- Zentra Foods, a mid-sized manufacturer, is considering a new automated packing line. The board has asked the operations director to produce …
- Zephyr Logistics is launching a new warehouse management system. Midway through the project, several departmental heads each ask for additio…
- Halden Logistics completed a new warehouse management system on the agreed date and within the approved budget, and it met every technical s…
- Halden Logistics is launching a warehouse automation project. The project manager has a team of experienced engineers who are keen and capab…
- Halden Telecom is building a new billing system. The project manager has agreed the scope, but during delivery, sales managers keep requesti…
- Lumen Foods is launching a new product line. The project risk register shows a risk with a low probability of occurring but a catastrophic i…