ACCA Strategic Professional · Strategic Business Leader · Leading and managing projects
Halden Logistics is launching a warehouse automation project. The project manager has a team of experienced engineers who are keen and capable but have never worked together. In the first weeks there is polite behaviour, uncertainty about roles and heavy reliance on the manager for direction. Under Tuckman's model of team development, which stage is the team in, and what leadership style is most appropriate?
The team is at the forming stage of Tuckman's model, shown by politeness, unclear roles and dependence on the manager. The most suitable approach is directive leadership, giving clear goals, structure and role definitions until the team gains confidence and cohesion.
- AForming; a directive style providing clear goals, roles and structureCorrect
- BStorming; a participative style to resolve conflict over roles
- CNorming; a delegating style as standards have been agreed
- DPerforming; a hands-off style as the team is self-managing
Explanation
Polite behaviour, uncertainty about roles and dependence on the leader are features of the forming stage. Here the leader should direct, clarifying objectives and roles. Storming would involve open conflict and challenge, which is not described.
Did you get it right without looking?
One question tells you little. A timed set on Leading and managing projects shows your real accuracy, how long you take and where you lose marks.
More Leading and managing projects questions
- Lumen Foods is launching a new product line. The project risk register shows a risk with a low probability of occurring but a catastrophic i…
- Marlow Pharma has just finished a three-year plant automation project. The board asks for a review to be held after the project's outputs ha…
- Marisol Retail is implementing a new customer data platform. A senior director, Mr Okafor, strongly influences budget decisions but has show…
- Brightwell Renewables is planning a solar farm build. The project manager has divided the project into deliverables (site preparation, panel…
- Marlow Council is planning a new public leisure centre. The sponsor insists on a fixed opening date and a fixed budget, but the stakeholders…
- Orlin Construction is building a hospital under a fixed-price contract. Midway, the client requests several additional features without form…