ACCA Strategic Professional · Strategic Business Leader · Leading and managing projects
Tavira Pharma is running a drug-packaging project. The project manager has a highly skilled team who are motivated, experienced and need little supervision, but who lack confidence in dealing with an unfamiliar regulator. According to Hersey and Blanchard's situational leadership, which style is most suitable?
A supporting style is best. Under Hersey and Blanchard, followers who are capable but lack confidence need high relationship behaviour and little task direction, so the leader encourages, listens and shares decision-making rather than instructing or fully delegating.
- ASupporting, with high relationship and low task direction, building confidenceCorrect
- BTelling, with high task direction and low relationship
- CDelegating, with low task and low relationship
- DSelling, with high task and high relationship
Explanation
The team has high competence but variable commitment or confidence, which calls for a supporting style: sharing decisions and encouraging with little direction. Telling suits low competence and delegating suits high competence and high commitment.
Did you get it right without looking?
One question tells you little. A timed set on Leading and managing projects shows your real accuracy, how long you take and where you lose marks.
More Leading and managing projects questions
- Zenara Foods plans to launch a new regional distribution hub. The board describes it as a one-off undertaking with a defined start and end d…
- Brindle Telecom is at the start of a customer-portal project. The project manager wants the sponsor to confirm early on that the project is …
- During a bank's core systems upgrade, the project team has entered a phase of open disagreement. Two senior analysts challenge the approach,…
- Corvane Engineering is running a large project. The sponsor wants it completed two months early without increasing cost or reducing quality.…
- Tessen Pharma completes the build and testing of a new data platform on time and within budget, and it meets the specification. Twelve month…
- Lumen Foods is launching a new product line. The project risk register shows a risk with a low probability of occurring but a catastrophic i…