Which statement about profit on an incomplete contract is correct under the conventional approach?
Under the conventional approach, no profit is taken to the Profit and Loss Account when work certified is below 25% of contract price, because the result is too uncertain. Prudence applies, and profit is recognised in part only as the contract progresses beyond that stage.
- ANo profit is taken to Profit and Loss Account if work certified is below 25% of contract priceCorrect
- BFull notional profit is always taken once 50% work is certified
- CProfit is taken only on completion of the contract
- DUncertified work is valued at selling price when computing notional profit
Explanation
Conventionally, if less than 25% is complete, no profit is credited because the outcome is uncertain; a fraction of profit is taken between 25% and 90%. Uncertified work is valued at cost, and full notional profit is not taken before near completion.
Did you get it right without looking?
One question tells you little. A timed set on Contract Costing shows your real accuracy, how long you take and where you lose marks.
More Contract Costing questions
- Materials costing Rs 2,00,000 were sent to a contract site and at the year end Rs 15,000 of materials were lost by theft and Rs 25,000 of ma…
- In contract costing, each contract is treated as a separate cost unit mainly because:
- A contract of ₹80,00,000 is 50% complete. Cost to date is ₹36,00,000, work certified is ₹40,00,000 and work uncertified is carried at cost o…
- Under the usual practice in contract costing, work uncertified is valued at:
- While executing a contract, the contractee orders additional work outside the original scope. The usual accounting treatment in contract cos…
- A contract has an escalation clause. The contractor's original estimate used materials Rs 10,00,000 and labour Rs 6,00,000. Actual material …