Skip to content

CMA Intermediate · Operations Management and Strategic Management · Project Management, Monitoring and Control

A project has a budgeted cost of work scheduled (planned value) of ₹8,00,000 to date, earned value of ₹6,40,000 and actual cost of ₹7,20,000. What are the schedule performance index (SPI) and cost performance index (CPI)?

SPI is 0.80 and CPI is about 0.89. SPI equals earned value divided by planned value, 6,40,000/8,00,000, and CPI equals earned value divided by actual cost, 6,40,000/7,20,000. Both below 1 show the project is behind schedule and over budget.

  1. ASPI 0.80; CPI 0.89Correct
  2. BSPI 0.89; CPI 0.80
  3. CSPI 1.25; CPI 1.12
  4. DSPI 0.80; CPI 1.12

Explanation

SPI = EV/PV = 6,40,000/8,00,000 = 0.80. CPI = EV/AC = 6,40,000/7,20,000 = 0.889, about 0.89. The option with SPI 0.89 and CPI 0.80 swaps the denominators. The project is behind schedule and over cost.

Did you get it right without looking?

One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.

More Project Management, Monitoring and Control questions