CMA Intermediate · Operations Management and Strategic Management · Project Management, Monitoring and Control
In PERT analysis, why is the probability of completion by a given date calculated using only the critical path's mean and variance?
PERT uses only the critical path because the longest path determines the project's completion time. Its summed expected times and variances are taken as the project's distribution. Non-critical activities have slack and are ignored in this approximation.
- ACritical path activities always have the smallest variance
- BThe project duration is governed by the longest path, so its distribution is taken to represent the projectCorrect
- CNon-critical activities have no time estimates
- DVariance of non-critical activities is always negative
Explanation
Project completion time is determined by the longest (critical) path, so PERT approximates the project duration by the sum of its activity means and variances. Critical activities need not have the smallest variance, and non-critical activities do have estimates; variance cannot be negative.
Did you get it right without looking?
One question tells you little. A timed set on Project Management, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.
More Project Management, Monitoring and Control questions
- A project has a total budget at completion (BAC) of ₹20,00,000. Earned value to date is ₹8,00,000 and actual cost is ₹10,00,000. Assuming th…
- In the project life cycle, which phase is mainly concerned with defining objectives, scope, deliverables and obtaining approval to proceed?
- In a PERT network, an activity has optimistic time 4 days, most likely time 7 days and pessimistic time 16 days. Using the beta-distribution…
- In the traditional project management 'triple constraint', a client of an Indian infrastructure firm demands that the scope be expanded mid-…
- Which tool breaks the total project scope into smaller, hierarchical, manageable deliverables and work packages?
- In a CPM project network, the critical path is best described as: