A Chennai firm budgets a project of 200 days. At day 100, monitoring shows 40% of the work done. If work continues at the same rate, how many total days will the project take, and what does this indicate?

The project will take 250 days and is 50 days behind schedule. Forty percent of the work in 100 days gives a rate of 0.4 percent per day, so completing 100 percent needs 250 days against a plan of 200. Monitoring reveals this gap while corrective action is still possible.

  1. A250 days; the project is behind schedule by 50 daysCorrect
  2. B200 days; the project is on schedule
  3. C160 days; the project is ahead of schedule by 40 days
  4. D300 days; the project is behind schedule by 100 days

Explanation

40% done in 100 days means 0.4% per day, so 100% needs 100/0.4 = 250 days. That is 50 days beyond the 200-day plan. Option 160 wrongly treats 40% as 40 days saved; 300 mistakenly adds 100 days.

Did you get it right without looking?

One question tells you little. A timed set on Communication, Co-ordination, Collaboration, Monitoring and Control shows your real accuracy, how long you take and where you lose marks.

More Communication, Co-ordination, Collaboration, Monitoring and Control questions